Latest Progress in Alor Star Area...
Tuesday, March 10, 2009
Tuesday, January 20, 2009
Tuesday, August 26, 2008
Wednesday, August 20, 2008
Sunday, August 3, 2008
Overall view for N3
RC Pile as a treatment for soft area in Kedah
Tuesday, July 22, 2008
Joint Measurement for the Month of July 2008
Joint Measurent will carry out before end of every Month. PMC need to verified the quantity of work or material before the claim can submit to the Client. Joint measurement will involved 3 party... (1) PMC(project Management Consultant (2) Consultant (to advise on technical matter) (3) Contractor
Sheet pile ready to claim, its already deliver to the Contractor Store yard at Gurun kedah.
Rebar at store yard, Gurun Kedah.